Saturday, March 31, 2012

A week of 03.26-03.30

+
The drawing for the next project was approved.
Lumber was rough milled and stickered.
I was working on writing procedure proposal.


++

The turning tools were horned and index bars for exercise and project were prepared.
I am ready for practice and turning.

Sunday, March 25, 2012

A week of 03.19-03.23

+
Bracket Feet, another lecture by Lance.


++
I brought lumber for my future projects, #2-#4. ;-)

+++
My #2 project drawing, Circular Console Table.

Wednesday, March 21, 2012

Saturday, March 10, 2012

A week of 03.05-03.09

+
A candle box, a proficiency test.
Total machine room hours are 1 hour and 40 minutes, total bench room hours are 17 hours and 20 minutes, summing up to 19 hours.
A long way to go to be really proficient.







Sunday, March 4, 2012

Project No. 1, Tool Chest

+
My first project in NBSS, a tool chest.

Wood: Mahogany
Finish: Linseed oil, Shellac, Wax
Dimension: 30" W, 14 1/4" H, 17" D

++
The beginning.





+++
The process.






















































++++

Finished tool chest.