+ Handrails
Handrails were installed.
Building work was going very slowly, however approaching to the end eventually.
dongilkim on blogger
Saturday, November 15, 2014
Thursday, November 13, 2014
Wednesday, November 12, 2014
A note on 11.12
+ Finishing aluminium walls
The aluminium panel walls were finished by caulking.
++ Landscaping work
Landscaping work was done on the rooftop and the ground.
+++ Turf block
Turf blocks were laid to create driveways.
The aluminium panel walls were finished by caulking.
++ Landscaping work
Landscaping work was done on the rooftop and the ground.
+++ Turf block
Turf blocks were laid to create driveways.
Friday, November 7, 2014
Wednesday, November 5, 2014
Saturday, November 1, 2014
A note on 11.01
+ Cleaning land
An excavator, a.k.a. poclaine cleaned land.
++ Windows and doors
Windows and doors were installed.
+++ Wooden floors
Wooden floors were installed and covered with papers.
An excavator, a.k.a. poclaine cleaned land.
++ Windows and doors
Windows and doors were installed.
+++ Wooden floors
Wooden floors were installed and covered with papers.
Thursday, October 30, 2014
A note on 10.31
+ Exterior work
Stucco was applied to the surfaces of the building. Insulation material was attached to the lightweight steel structured walls. Scaffolding was removed.
++ Painting
Inside walls was painted.
+++ Manholes and drain pipes
Manholes for water, electricity, communication were made. Drain pipes were installed.
++++ Epoxy floor
Self-leveling mortar was coated to make the base of the epoxy floor.
Stucco was applied to the surfaces of the building. Insulation material was attached to the lightweight steel structured walls. Scaffolding was removed.
++ Painting
Inside walls was painted.
+++ Manholes and drain pipes
Manholes for water, electricity, communication were made. Drain pipes were installed.
++++ Epoxy floor
Self-leveling mortar was coated to make the base of the epoxy floor.