+ Exterior work
Stucco was applied to the surfaces of the building.
Insulation material was attached to the lightweight steel structured walls.
Scaffolding was removed.
++ Painting
Inside walls was painted.
+++ Manholes and drain pipes
Manholes for water, electricity, communication were made.
Drain pipes were installed.
++++ Epoxy floor
Self-leveling mortar was coated to make the base of the epoxy floor.