Sunday, March 4, 2012

Project No. 1, Tool Chest

+
My first project in NBSS, a tool chest.

Wood: Mahogany
Finish: Linseed oil, Shellac, Wax
Dimension: 30" W, 14 1/4" H, 17" D

++
The beginning.





+++
The process.






















































++++

Finished tool chest.









A week of 02.28-03.02

+
The panel was protected by masking tape and wax paper and the panel and frame was glued up.


Pins were installed.


A finger grip was carved.


The lock was installed.

++
Lance gave a lecture on drop leaves.
Since I was considering building a card table, it was most interesting topic to me.




+++
The tool chest was going to the finishing room, and getting finish, linseed oil, shellac, wax.


+++
My first project in NBSS, a tool chest was finished.
I was glad that it was done without major accidents or mistakes. ;-)








Wednesday, February 29, 2012

Trip to NY

+
I made a short trip to NY to see a Duncan Phyfe exhibition at the Metropolitan Museum of Art.
The furniture pieces were awesome.
Unfortunately photography was prohibited. Sigh.




++
One reality, however is it a dream?

Sunday, February 26, 2012

A week of 02.20-02.24

+
Philip Lowe gave a slide presentation on his work and his new school and Joseph Karagezian, a French upholsterer gave a presentation on upholstering a Sheraton side chair made by Timm.
Philip Lowe's apprenticeship program was my second option before I came here. I also enjoyed his DVD presentation on making reeding of a Sheraton chair using a lathe indexing system, which was similar to Lace's presentation.
The upholstery presentation was awesome, which I always wanted to see at some time. Still many thing are unclear, but I have an idea now.












++
The frame was made, and the panel was smoothed.


The raised panel was made on a table saw.
Burning was created by my sloppy feather board setting-up. Sigh. However it was cleanly removed by planing. ;-)



Check fitting of the panel and frame.


Linseed oil was applied on the panel and shellac and wax will be followed.

+++
The ship-lap backs and drawer stops were made.


The notches for drawer bottom screws were made.


Drawer stops were installed.


The case outside surfaces were planed, sanded.


Now the case is smooth.