Tuesday, October 7, 2014

A note on 10.08

+ More measures to prevent water leakage

Waterproofing was applied to the walls of the basement and the rooftop.
Drain boards were installed on the basement floor for displacement of potential water leakage if any.





++ Plumbing

Water and sewage pipes were installed.





+++ Air conditioner work

Pipes and conduits for air conditioners were installed.




++++ Concrete

A layer of concrete was poured to cover the drain boards of the basement. Same was done over the waterproofing of the rooftop for protection.




+++++ Brickwork

Brickwork was being done to make bathrooms and a 1st floor wall.




++++++ Aerated concrete

Aerated concrete was laid on at the basement and the 2nd floor. The bubbles in the aerated concrete would help insulation between concrete frame and floor heating system.




+++++++ Window and door frames

Window and door frames were installed.